In order to import linked elements through the spreadsheet you need to populate your excel file according to the following information. If you would like to get a sample template of the excel file, please press the corresponding link for the type of import; with or without drawings (Linked_template.xlsx or IMPACT_import_file_drawings.xlsx).

  1. It is necessary to start adding information from Row number 2.
  2. Fields that are marked with blue, is MANDATORY to fill them out with information for the import to work
  3. Fields that are marked with orange, is NOT MANDATORY to fill them out with information for the import to work. The software will either assign them automatically or leave the field empty in the database.
  4. Floors, Building, and Phases need to be Pre-Defined in the Project Manager, before the import. The excel file will not create new phases, floors, or buildings and it will probably give an error.
  5. If an error occurs, please check the log for more information. There is always a better description of why the import was not executed correctly.
  6. On row 2, in the tables underneath, wherever there is a comment called "No.", it means that only numbers and NO letters are accepted.
  7. For the number fields, you can add decimals according to your excel settings (not for IMPACT Sum though)
  8. For IMPACT Factory and Division make sure that the name on the excel file is the exact same as the one in your database.
  9. For Multiple Drawing Layouts/Prefixes make sure to separate them with this symbol (;)
 ABCDEFGHIKLMN
1IMPACT Element MarkIMPACT SumIMPACT Overall LengthIMPACT Overall WidthIMPACT Overall HeightIMPACT Overall AreaIMPACT Overall MassIMPACT GroupIMPACT TimeIMPACT CostIMPACT FactoryIMPACT DivisionIMPACT Building
2Letter+No.No. (without decimals)No.No.No.No.No.Letters/No.No.No.Letters/No.Letters/No.Letters/No.
 OPQRSTUVW
1IMPACT FloorIMPACT No. of StrandsIMPACT RemarkIMPACT ProductIMPACT VolumeDrawing NameLayout Prefix/SufixRevision NameRevision Date
2Letters/No.No.Letters/No.Letters/No.No.LettersLetters separated by ;(symbol) for multipleLetters/No.Date Format DD/MM/YYYY

Import Linked without Drawings

The information on the excel file should look like in the following picture. Download the sample excel file press here: Linked_template.xlsx

1588750277747-254.png

In order to import linked elements with the use of the spreadsheet above, then you need to follow the next steps:

  • Right-click on Element marks and select Import Linked (You can also select "Import Linked" from the Project Manager Menu)

1588749176005-169.png

  • Import/Update Element Marks and Elements

1588749665142-951.png

  • Select Source File(s)... / Select the excel file that you would like to import and press the "Import" button.

1588749978530-113.png

  • Elements should now be visible on your Project Manager

1588750686863-909.png

Import Linked with DWG and PDF files

The information on the excel file should look like in the following picture. The columns in blue are the ones added to the original spreadsheet. Download the sample excel file press here: IMPACT_import_file_drawings.xlsx

1588750947912-777.png

In order to import the elements from the spreadsheet above you need to follow the next steps:

  • Right-click on Element marks and select Import Linked (You can also select "Import Linked" from the Project Manager Menu)

1588749176005-169.png

  • Import/Update Element Marks, Elements and Drawings

1588751843458-589.png

  • Select Source File(s)... and Select Drawing Folder/ It is very important to select the folder with all the drawings included both in DWG and PDF format.

1588752224092-494.png

The files in the folder should like in the following picture (with respect to the example file).

1588753210431-116.png

IMPORTANT: Different layouts should be included in the DWG file and not in the name of the DWG file. Different layouts should be included at the end of the name in PDF files in order to be imported into IMPACT. Revisions and Dates do not need to be included in the name of the files.

  • After pressing "Import" you can open the log and see if the drawings were transferred successfully

1588753929868-273.png

After importing the files, the drawings and the corresponding layouts will be added under the "Drawings" tab in PM. In order to see the different layouts, you need to right-click on a drawing and press "Layouts".

1588757101446-757.png

  • Now you can right-click on the elements on the Model Viewer, "Open Drawings" and select one of the following options shown in the picture.

1588754060236-652.png

Opening PDF files will always allow you to select between the different layouts.

1588757575686-394.png

1588754694886-529.png

An alternative to the method above is that you can import elements through the Start tab in Project Manager. The process is the exact same

1588756397490-523.png