Cost Estimation

Last modified by Adam Carlson on 2021/09/20 16:15

Introduction

The cost estimation report contains information about the element mark, net area, manual time, total cost, total time, sum etc. 

Production report that can be printed from the Cost Estimation.

Report Setup

General report setup. All the fields have to be filled if you need a sum row at the end of the page.

1.png

Page max X and Page max Y defined the maximum size of the report page.
The X-axis is the columns A, B, C etc. The Y-axis is the rows 1, 2, 3 etc.

Continuous Header Row defines in which row the header and footer start, and in this case, it starts from row 6.

Continuous Start Row (in this case from row 8) is where the main information starts and Continuous End Row (in this case until row 27) is where the main information ends.
If the last field is filled a summary for each page will be created at the end of the page.

Header setup: 

Here is how the header is set up for this report.

2.png

As you can see we have different X and Y values for each field. This is done so the program knows where to put the specific information into the report.

As mention above, the continuous header starts at row 8 to row 27 in the Y direction.

Here are the fields that can be added to the Header and Footer:

FieldsDescription
PROJECT 
PROJECT_ID 
PROJECT_SUMMARY 
REPORT_PAGE_NUMBER 
REPORT_PRINT_DATE 
USER_DIVISION_CITY 
USER_DIVISION_COUNTRY 
USER_DIVISION_DESCRIPTION 
USER_DIVISION_FAX 
USER_DIVISION_NAME 
USER_DIVISION_PHONE 
USER_DIVISION_STREET 
USER_DIVISION_ZIPCODE 
USER_MOBILE 
USER_NAME 
USER_PHONE 
USER_SIGNATURE 
USER_TITLE 

Selection setup:
The standard setup for the selections.

Continuous setup:

The Continuous setup is where you set up all the information, in this case, about the Cost Estimation.

3.png

As you can see, here you define only one row because this row will be the basis for this report, from row 8 to 27 as shown further up. 

The fields you can add to this section are listed below

ANGLE_LEFT_SIDE 
ANGLE_RIGHT_SIDE 
BaseTime 
BOUNDING_BOX_AREA 
BUILT_THICKNESS 
CHANGED_BY 
CHANGED_DATE 
CimCost 
CimTime 
ConcreteCost 
CREATED_BY 
CREATED_DATE 
DESIGNATION 
ELEMENT_GRP 
ELEMENT_HEIGHT 
ELEMENT_LENGTH 
ELEMENT_MARK 
ELEMENT_RADIUS 
ELEMENT_TYPE 
ELEMENT_WIDTH 
ENDCAP_COST 
ENDCAP_TIME 
FORM_WIDTH 
FormCost 
FormTime 
GROSS_AREA 
INSULATION_TIME 
InsulationCost 
ManualCost 
ManualTime 
MASS 
MATERIAL 
MaterialCost 
NET_AREA 
OpeningCost 
OpeningTime 
OPERATING_COST_COMPANY 
OPERATING_COST_PRODUCT 
PRODUCT 
PROJECT 
RCCost 
RCTime 
REMARK 
RIDGE_DISTANCE 
RIDGE_TYPE 
STYLE 
SUM 
SURFACE_COST 
SURFACE_TIME 
TOLERANCE 
TotalCost 
TotalTime 
WEIGHT 
WorkingCost 

Print report

From Cost Estimation
This report can be printed from the Cost Estimation as shown here.

You right-click on one or several elements and select "Print All/Selected Element Marks"

4.png

Example

5.png