Introduction

The report summarises the whole project.  

Design / Production report that can be printed from Report Tool & Resource Manager.

Report Setup

General report setup. All the fields have to be filled in for the sum row at the end of each page to print.

12023-03-01 08_48_45-Window.png

Page max X and Page max Y defined the maximum size of the report page.
The x-axis is the columns A, B, C, and etc. and the Y-axis is the rows 1, 2, 3, and etc.

Continuous Header is defined in which row the header and footer start, and in this case, it starts from row 10.

Continuous start row (in this case it is row 12) is where the main info starts and ends in the Continuous end row(in this case it is row 0)
There is no summary for this report.

Header setup: 
Here is how the header is set up for this report.

22023-03-01 08_51_46-Window.png

As you can see we have those x and y values for each field, so the program knows where to put the specific information into the report.

As mentioned above, the Continuous header starts at row 10 to row 0 in the Y direction.

Here are the fields that can be added to the Header and footer:

FieldsDescription
BUILDING 
DIVISION 
FACTORY 
FLOOR 
PHASE 
PROJECT 
PROJECT_SUMMARY 
PROJECT_TRIMED 
REPORT_NAME 
REPORT_PAGE_NUMBER 
REPORT_PRINT_DATE 
REPORT_REVISION 
REPORT_REVISION_DATE 
REPORT_TITLE 
SELECTION_PRODUCT 
USER_DIVISION_CITY 
USER_DIVISION_COUNTRY 
USER_DIVISION_DESCRIPTION 
USER_DIVISION_FAX 
USER_DIVISION_NAME 
USER_DIVISION_PHONE 
USER_DIVISION_STREET 
USER_DIVISION_ZIPCODE 
USER_MOBILE 
USER_NAME 
USER_PHONE 
USER_SIGNATURE 
USER_TITLE 

Continuous setup:

Here in Continuous setup is where you set up all the information about holes in this case.

32023-03-01 08_52_38-Window.png

As you can see, here you define only one row because this row will be the bases for this report, from row 12 to 0 like shown further up. 

The fields you can add to this section are listed below.

FieldsDescription
BEND_RC 
BEND_RC_MESH 
BOUNDING_BOX_AREA 
BUILDING 
CAST_IS_REPORTED(New in Q2/2023)
CAST_REPORTED_COST(New in Q2/2023)
CAST_REPORTED_DATE(New in Q2/2023)
COST_PR_SQUAREMETER 
DELIVERY_DATE 
DOORS 
ELEMENT_GROUP 
ELEMENT_ID 
ELEMENT_MARK 
ELEMENT_TYPE 
EXTENSION_BACK 
EXTENSION_BOTTOM 
EXTENSION_FRONT 
EXTENSION_LEFT 
EXTENSION_RIGHT 
EXTENSION_TOP 
FACTORY 
FLOOR 
GROSS_AREA 
HEIGHT 
HOLES_LARGE 
HOLES_MEDIUM 
HOLES_SMALL 
INSULATION_AREA 
INSULATION_MATERIAL 
INSULATION_THICKNESS 
INSULATION_VOLUME 
LENGTH 
MASS 
NET_AREA 
NOTES 
NOTE2(New in Q2/2023)
NOTE3(New in Q2/2023)
NOTE4(New in Q2/2023)
PHASE 
PLANNED_DELIVERY_DATE 
PLANNED_DRAWING_DATE 
PLANNED_ERECTION_DATE 
PLANNED_PRODUCTION_DATE 
PRODUCT 
PRODUCTION_DATE 
PRODUCTION_FACTORY_NAME 
PROJECT 
REINFORCEMENT_GROUP 
REINFORCEMENT_MESH 
STATUS 
STRAIGHT_RC 
STRAND_DIAMETER 
STRAND_LENGTH 

TOTAL_CONCRETE_VOLUME

(New in Q2/2023)
TOTAL_COST 
TOTAL_HEIGHT 
TOTAL_LENGTH 
TOTAL_TIME 
TOTAL_WIDTH 
TRANSPORT_ID 

VOLUME_INNER_PANEL

(New in Q2/2023)

VOLUME_OUTER_PANEL

(New in Q2/2023)
W_CIM_TABLE 
WIDTH 
WINDOWS 

Print report

From Report Tool
It is possible to make the normal selection on what to print, based on the information you want to get out of the report.

You also have the option to save your selection.

42023-03-01 08_56_13-Window.png

From Resource Manager
Planning -> Right-click -> Print -> Element follow up (Same as Project Follow-Up)

52023-03-01 08_21_26-17_LOCAL_DB -  - IMPACT Project Manager.png

Example

62023-03-01 08_56_54-Project Follow-Up0.xlsx - Excel.png

Download

You can download the report template here

Copyright 2024 StruSoft AB
IMPACT Wiki