Reinforcement Specification

Last modified by Adam Carlson on 2025/10/20 13:35

Reinforcement used in the project is shown, displaying the total number of it per element mark.

If an element type contains more than 10 element marks, the content is divided across multiple pages.

Each page or document includes a maximum of 10 element marks, with subsequent marks continuing on the next page.

This is both a production and a design report that can be printed from Report Tool and Project Manager

Report Setup

General report setup. All the fields have to be filled as it prints a sum row at the end of each page.

1r.png

Figure 1: General report layout

Page max X and Page max Y define the maximum dimensions of the report page. 

The X-axis corresponds to columns labeled A, B, C, etc., while the Y-axis represents rows numbered 1, 2, 3, etc.

Continuous Header Row specifies the starting row for both the header and footer. In this configuration, it begins at row 10.

Continuous Start Row, set to row 11, marks the beginning of the main content. 

Continuous End Row, set to row 40, indicates where the main content concludes.

If the final field is completed, a summary will be generated at the end of each page.

Header setup: 
Here is how the header is set up for this report.

2r.png

Figure 2: Header and footer report setup

Assigning x and y values to each field facilitates the precise placement of designated information within the report.

As previously stated, the Continuous Header Row spans from row 0 to row 10 along the Y-axis.

The following fields are available for inclusion in the header and footer sections:

FieldsDescription
BUILDING 
DIVISION 
FACTORY 
PHASE 
PROJECT 
PROJECT_SUMMARY 
PROJECT_TRIMED 
REPORT_NAME 
REPORT_PAGE_NUMBER 
REPORT_PRINT_DATE 
REPORT_REVISION 
REPORT_REVISION_DATE 
REPORT_TITLE 
SELECTION_PRODUCT 
USER_DIVISION_CITY 
USER_DIVISION_COUNTRY 
USER_DIVISION_DESCRIPTION 
USER_DIVISION_FAX 
USER_DIVISION_NAME 
USER_DIVISION_PHONE 
USER_DIVISION_STREET 
USER_DIVISION_ZIPCODE 
USER_MOBILE 
USER_NAME 
USER_PHONE 
USER_SIGNATURE 
USER_TITLE 

Selection setup:
The standard setup for the selections.

Continuous setup:

All element-related configurations are managed within the Continuous setup section.

3r.png

Figure 3: Continuous report setup

As previously demonstrated, a single row is defined within this section, serving as the foundation for the report and extending from row 11 to row 40.

The fields available for inclusion in this section are listed below.

FieldsDescription
CUTLENGTH 
CUTLENGTH_ROUNDED 
DIAMETER 
MASS 
MASS_MESH_PER_M2 
MESH_TYPE 
NUMBER_OF_PER_ELEMENT 
QUALITY 
RC_AREA 
RC_NAME 
RC_WIDTH 
SUM 

Print report

Information about where the report can be printed from.

From Report Tool

It is possible to select a standard set of content to be printed based on the information extracted from the report.

An option is also provided to save the selection.

4r.png

Figure 4: Print report setup - Report tool

From Project Manager

The report is accessible for printing directly from the model viewer.

1760960126681-301.png

Figure 5: Print report setup - Project Manager

Example

Printed page displayed below in Excel. 

5r.png

Figure 6: Excel report page

Download

You can download the report template here