Transport Overview

Last modified by Dennis Knudsen on 2023/05/22 11:26

Introduction

The transport overview report contains information about the projects transport number, delivery date, weight, additional items, element mark, and amount. 

Production report that can be printed from the Transport Planning.

Report Setup

General report setup. All the fields have to be filled if you need a sum row at the end of the page.

1s.png

Page max X and Page max Y defined the maximum size of the report page.
The X-axis is the columns A, B, C etc. The Y-axis is the rows 1, 2, 3 etc.

Continuous Header Row defines in which row the header and footer start, and in this case, it starts from row 6.

Continuous Start Row (in this case from row 7) is where the main information starts and Continuous End Row (in this case until row 40) is where the main information ends.
If the last field is filled a summary for each page will be created at the end of the page.

Header setup: 

Here is how the header is set up for this report.

2s.png

As you can see we have different X and Y values for each field. This is done so the program knows where to put the specific information into the report.

As mention above, the continuous header starts at row 6 to row 6 in the Y direction.

Here are the fields that can be added to the Header and Footer:

FieldsDescription
BUILDING_OWN_NAME 
BUILDING_SITE_NAME 
LOADING_DURATION(New in Q1/2023)
PROJECT_H 
PROJECT_MANAGER 
PROJECT_SUMMARY 
REPORT_PAGE_NUMBER 
REPORT_PRINT_DATE 
UNLOADING_DURATION(New in Q1/2023)
USER_DIVISION_CITY 
USER_DIVISION_COUNTRY 
USER_DIVISION_DESCRIPTION 
USER_DIVISION_FAX 
USER_DIVISION_NAME 
USER_DIVISION_PHONE 
USER_DIVISION_STREET 
USER_DIVISION_ZIPCODE 
USER_MOBILE 
USER_NAME 
USER_PHONE 
USER_SIGNATURE 
USER_TITLE 

Selection setup:
The standard setup for the selections.

Continuous setup:

The Continuous setup is where you set up all the information, in this case, about the Transport Overview.

3s.png

As you can see, here you define only one row because this row will be the basis for this report, from row 7 to 40 as shown further up. 

The fields you can add to this section are listed below

ACTUAL_DELIVERY_DATE(New in Q1/2023)
BIGGEST_ELEMENT_LENGTH 
BIGGEST_ELEMENT_THICKNESS 

BIGGEST_ELEMENT_TOTAL_LENGTH

(New in Q2/2023)

BIGGEST_ELEMENT_TOTAL_THICKNESS

(New in Q2/2023)
BIGGEST_ELEMENT_TOTAL_WIDTH(New in Q2/2023)
BIGGEST_ELEMENT_WIDTH 

TOTAL_TOTAL_WIDTH

(New in Q2/2023)
BUILDINGS 
DELIVERY_ADDRESS1 
DELIVERY_ADDRESS2 
DELIVERY_CITY 
DELIVERY_COUNTRY 
DELIVERY_DATE 
DELIVERY_ZIPCODE 
DIVISION 
ELEMENT_COUNT 
ELEMENT_ID 
ELEMENT_MARK 
ELEMENT_MARK_ERECTIONSEQUENS_ORDER 
FACTORY 
FLOORS 
IS_JOINED 
LOAD_DATE 
NO_OF_ADDITIONAL_ITEM 
NO_OF_STACKS 
NO_OF_STOCK_ITEMS 
NO_OF_VEHICLES 
NOTE 
NOTE2(New in Q2/2023)
NOTE3(New in Q2/2023)
NOTE4(New in Q2/2023)
PRICE_LIST 
PROJECT 
PROJECT_NAME 
QR_CODE 
REMARK 
STACK_NOS 
STACKS 
TEXT1 
TEXT2 
TEXT3 
TEXT4 
TOTAL_ADDITIONAL_ITEM_MASS 
TOTAL_MASS 
TOTAL_WIDTH 
TRANSPORT_DESCRIPTION 
TRANSPORT_ID 
TRANSPORT_NO 
TRANSPORT_STATUS 
TRANSPORT_USAGE 
VEHICLE 

Print report

From Transport Planning
This report can be printed from the Project Manager as shown here and also from the Resource Manager.

You right-click on a transport and select print "Transport Planning..."

4.png

Example

5s.png

Download

You can download the report template here