Planning

Version 6.1 by KristoferHellman on 2019/02/04 15:58

The planning tab of the Project Manager consists of four major parts:

  • Filter and properties

  • Cast Planning module

  • Stack Planning module

  • Transport Planning module

The four parts are highlighted in blue, see figure 1 below.

1549291400589-345.png

Figure 1, the planning tab, from the left: Filter and properties, Cast, Stack and Transport Planning modules

The element id grid is also visible in figure 1, the filter tab can be used to filter out element ID's. These element ID's may be manipulated further by making use of the filters in the ID-grid itself.

Using the Planning tab

As the planning tab makes element ID's searchable and sortable, the main task of the Planning tab is to enable the Cast, Stack and Transport planning of elements.