Inventory Project

Last modified by Adam Carlson on 2022/08/09 10:38

Introduction

The Inventory Project report contains information about the factory, project, division, storage location, element count, status, total mass, etc. 

Production report that can be printed from the storage tab in resource manager.

Report Setup

General report setup. All the fields have to be filled if you need a sum row at the end of the page.

1w.png

Page max X and Page max Y defined the maximum size of the report page.
The X-axis is the columns A, B, C etc. The Y-axis is the rows 1, 2, 3 etc.

Continuous Header Row defines in which row the header and footer start, and in this case, it starts from row 10.

Continuous Start Row (in this case from row 11) is where the main information starts and Continuous End Row (in this case until row 40) is where the main information ends.
If the last field is filled a summary for each page will be created at the end of the page.

Header setup: 

Here is how the header is set up for this report.

2w.png

As you can see we have different X and Y values for each field. This is done so the program knows where to put the specific information into the report.

As mention above, the continuous header starts at row 10 to row 10 in the Y direction.

Here are the fields that can be added to the Header and Footer:

FieldsDescription
FACTORY 
REPORT_PAGE_NUMBER 
REPORT_PRINT_DATE 
USER_DIVISION_CITY 
USER_DIVISION_COUNTRY 
USER_DIVISION_DESCRIPTION 
USER_DIVISION_FAX 
USER_DIVISION_NAME 
USER_DIVISION_PHONE 
USER_DIVISION_STREET 
USER_DIVISION_ZIPCODE 
USER_MOBILE 
USER_NAME 
USER_PHONE 
USER_SIGNATURE 
USER_TITLE 

Selection setup:
The standard setup for the selections.

Continuous setup:

The Continuous setup is where you set up all the information, in this case, about the Inventory Project.

3w.png

As you can see, here you define only one row because this row will be the basis for this report, from row 11 to 40 as shown further up. 

The fields you can add to this section are listed below:

FieldsDescription
DESCRIPTION 
DIVISION 
ELEMENT_COUNT 
PROJECT 
PROJECT_NAME 
STATUS 
STORAGE_LOCATION 
TEXT3 
TEXT4 
TEXT5 
TEXT6 
TOTAL_BOUNDING_BOX_AREA 
TOTAL_GROSS_AREA 
TOTAL_MASS 
TOTAL_NET_AREA 
TOTAL_PRICE 
TOTAL_TIME 

Print report

From the Storage tab in Resource Manager.
This report can be printed from Resource Manager as shown below.
Note: It is called Per Project Report when printed

4w.png

Example

5w.png

Download

You can download the report template here