IMPACT Production - Training Material

Last modified by Thomas Gitsas on 2024/04/12 11:45

This is an extended course of IMPACT Production in version 17.1, where most features and workflows are explained in detail. The course is carried out using a Sample Project, which will be provided in the training under the corresponding chapter. It is also recommended to be connected to IMPACT's cloud trial and training database (details will be given out to all participants by the course leader). For those who are using their own IMPACT environment, further steps regarding settings need to be taken.

This course does not require any prior knowledge of IMPACT or IMPACT Production and everyone can follow as long as they are connected to an IMPACT environment.

In the training material, there are many "Notes" and "IMPORTANT Notes" that are used to emphasise tips and tricks that will be useful during the training. The first IMPORTANT note can be found below.

IMPORTANT Note: This training is using primarily Text to explain all the functions and features of IMPACT Production. The pictures and movie files support the text and not the opposite. Looking only at the pictures, will not be beneficial for completing this training. 

You can START the training by pressing HERE.

Table of contents

  1. Introduction/Objective/Elements in IMPACT
  2. Create a Project, Add Rough Planning settings, Activate Modules
  3. The Project Manager's main functionalities and Layouts are explained. Create your layout.
  4. Project Browser Overview (Create Buildings/Floors, Import Linked or Import project)
  5. Create Production Statuses in RM – (If you demo a trial license on StruSoft`s cloud database, you can skip this step. We have already set this up for you).
  6. Import Reports in Report Tool – (If you demo a trial license on StruSoft`s cloud database, you can skip this step. We have already set this up for you).

Rough Planning Phase

  1. Cranes
  2. Erection Planning
  3. Rough Planning

Performance Phase (Fine Planning)

  1. Cast Planning
  2. Element Control
  3. Disorders/Rejections/Notifications
  4. Storage
  5. 3D Stack and Transport Planning
  6. Elements Delivered and Erected on-site
  7. Summary Excercise (Plan floors 2,3 and 4)