Transport items
Introduction
The Transport items report contains information about company transport id, delivery note id, reinforcement, CIMs etc.
Report Setup
General report setup. All the fields have to be filled if you need a sum row at the end of the page.
Page max X and Page max Y defined the maximum size of the report page.
The X-axis is the columns A, B, C etc. The Y-axis is the rows 1, 2, 3 etc.
Continuous Header Row defines in which row the header and footer start, and in this case, it starts from row 11.
Note that in this report the header is added in the report tool itself and not in the template file.
Continuous Start Row (in this case from row 12) is where the main information starts and Continuous End Row (in this case until row 40) is where the main information ends.
If the last field is filled a summary for each page will be created at the end of the page.
Header setup:
Here is how the header is set up for this report.
As you can see we have different X and Y values for each field. This is done so the program knows where to put the specific information into the report.
Here are the fields that can be added to the Header and Footer:
Fields | Description |
EXTERNAL_FACTORY_NAME | |
EXTERNAL_PROJECT_NAME | |
FACTORY | |
FIRST_DELIVERY_DATE | |
LAST_DELIVERY_DATE | |
PROJECT | |
PROJECT_NAME | |
PROJECT_SUMMARY | |
REPORT_PAGE_NUMBER | |
REPORT_PRINT_DATE | |
USER_MOBILE | |
USER_NAME | |
USER_PHONE | |
USER_SIGNATURE | |
USER_TITLE |
Selection setup:
The standard setup for the selections.
Continuous setup:
The Continuous setup is where you set up all the information, in this case, about the Cast Calendar.
As you can see, here you define only one row because this row will be the basis for this report, from rows 12 to 40 as shown further up.
Fields marked with X are repeated as needed based on how many transports are selected.
The fields you can add to this section are listed below:
Fields | Description |
DESCRIPTION | |
ITEM | |
NAME | |
UNIT | |
X_COMPANY_TRANSPORT_ID | |
X_DELIVERY_NOTE_ID | |
X_DUMMY | Not used at the moment. |
X_QUANTITY | |
X_TOTAL_MASS |
Print Report
From the transport planning in Resource Manager & Project Manager.
This report can be printed as shown below.