Concrete Mix Check
Last modified by Dennis Knudsen on 2025/03/04 10:06
Required Setting
Before the IMPACT Sync does the "Concrete Mix Check"(For more information about the Concrete Mix Check - Click Here), is it needed to have the project property "Autocheck Concrete Mix" set to Yes.

Furthermore, it is also needed to add the Concrete Mix Configuration to the Config file for the Sync. The configuration can be found under "Configuration".
When these two things are configured, will the IMPACT Sync perform a "Concrete Mix Check" on the selected time(s).
Configuration
- !--For Concrete Mix Check (52)-->
- <add key ="ConcreteMixCheckRequireReadyForProduction" value="No"/>
- <!-- Element types -->
- <add key="ConcreteMixCheckBeam" value="No" />
- <add key="ConcreteMixCheckColumn" value="No" />
- <add key="ConcreteMixCheckDoubleWall" value="No" />
- <add key="ConcreteMixCheckFormSlab" value="No" />
- <add key="ConcreteMixCheckHollowCore" value="No" />
- <add key="ConcreteMixCheckInsulatedWall" value="No" />
- <add key="ConcreteMixCheckLinked" value="No" />
- <add key="ConcreteMixCheckPrestressedBeam" value="No" />
- <add key="ConcreteMixCheckPrestressedFormSlab" value="No" />
- <add key="ConcreteMixCheckPrestressedLinked" value="No" />
- <add key="ConcreteMixCheckPrestressedSlab" value="No" />
- <add key="ConcreteMixeCheckSandwich" value="No" />
- <add key="ConcreteMixCheckSlab" value="No" />
- <add key="ConcreteMixCheckWall" value="No" />
- <!--ConcreteMix Check filter: Limit calculation to certain standard(s) and project(s) separated by "," -->
- <add key="ConcreteMixCheckFactory" value="1101" />
- <add key="ConcreteMixCheckProjectPrefix" value="" />
- <!--For Concrete Mix Check End-->
Details
When the Sync has been performed, will the latest update show in the project properties along with info in the Resource Manager.