Reinforcement Follow up

Last modified by Adam Carlson on 2025/10/20 14:51

This report summarize all reinforcement types and specifies the members of a Reinforcement Group. 

When printed from production, a set of data will be generated for each project. There is one document for each element type. 

This is both a production and a design report that can be printed from Report Tool, Project Manager, and Resource Manager

Report Setup

General report setup. All the fields have to be filled as it prints a sum row at the top of each page.

1715062626211-545.png

Figure 1: General report layout

Page max X and Page max Y define the maximum dimensions of the report page. 

The X-axis corresponds to columns labeled A, B, C, etc., while the Y-axis represents rows numbered 1, 2, 3, etc.

Continuous Header Row specifies the starting row for both the header and footer. In this configuration, it begins at row 5.

Continuous Start Row, set to row 7, marks the beginning of the main content. 

Continuous End Row, set to row 40, indicates where the main content concludes.

If the final field is completed, a summary will be generated at the top of each page.

Header setup: 
Here is how the header is set up for this report.

1715062783625-164.png

Figure 2: Header and footer report setup

Assigning x and y values to each field facilitates the precise placement of designated information within the report.

As previously stated, the Continuous Header Row spans from row 0 to row 5 along the Y-axis.

The following fields are available for inclusion in the header and footer sections:

FieldsDescription
BUILDING 
DIVISION 
ELEMENT_TYPE 
FACTORY 
FLOOR 
PHASE 
PROJECT 
PROJECT_SUMMARY 
PROJECT_TRIMED 
REPORT_NAME 
REPORT_PAGE_NUMBER 
REPORT_PRINT_DATE 
REPORT_REVISION 
REPORT_REVISION_DATE 
REPORT_TITLE 
SELECTION_PRODUCT 
USER_DIVISION_CITY 
USER_DIVISION_COUNTRY 
USER_DIVISION_DESCRIPTION 
USER_DIVISION_FAX 
USER_DIVISION_NAME 
USER_DIVISION_PHONE 
USER_DIVISION_STREET 
USER_DIVISION_ZIPCODE 
USER_MOBILE 
USER_NAME 
USER_PHONE 
USER_SIGNATURE 
USER_TITLE 

Selection setup:
The standard setup for the selections.

Continuous setup:

All element-related configurations are managed within the Continuous setup section.

There is also a field for the Header Name, as the report is generated dynamically.

1715063079841-878.png

Figure 3: Continuous report setup

As previously demonstrated, a single row is defined within this section, serving as the foundation for the report and extending from row 7 to row 40.

The fields available for inclusion in this section are listed below.

FieldsDescription
ALL_MEASUREOne text for all the measures on bended reinforcement
CUTLENGTH 
CUTLENGTH_ROUNDED 
DIAMETER 
END_HOOK_1_DIRECTION 
END_HOOK_1_NAME 
END_HOOK_2_DIRECTION 
END_HOOK_2_NAME 
JIG_RADIUS 
MASS 
MASS_MESH_PER_M2 
MEASURE_TABLE 
MESK_TYPE 
NO_IN_GROUP 
QUALITY 
RC_AREA 
RC_NAME 
RC_TYPE 
RC_WIDTH 
REMARK 
REVISION 
SHAPE_CODE 
SHAPE_PICTURE 
SUM 
X_ELEMENT_MARK_TABLE 

Print report

Information about where the report can be printed from.

From Report Tool

It is possible to select a standard set of content to be printed based on the information extracted from the report.

An option is also provided to save the selection.

1715069235932-455.png

Figure 4: Print report setup - Report tool

A dedicated selection section allows specification of the type of reinforcement to be included in the report.

1715069292118-340.png

Figure 5: Dedicated selection section

From Project Manager

The report is accessible for printing directly from the model viewer & from the element ids tab.

1715069327517-622.png

Figure 6: Print report setup - Project Manager - Model View

1760964621066-667.png

Figure 7: Print report setup - Project Manager - Element Ids

Selection of reinforcement types is required for inclusion in the report.

1715069362506-885.png

Figure 8: Selection of reinforcement types - Project Manager

From Resource Manager

The report is accessible for printing directly from the planning tab.

1715069488818-780.png

Figure 9: Print report setup - Resource Manager - Planning

Selection of reinforcement types is required for inclusion in the report.

1715069542929-970.png

Figure 10: Selection of reinforcement types - Resource Manager

Example

Printed page displayed below in Excel.

1715089359157-944.png

Figure 11: Excel report page

Download

You can download the report template here