Reinforcement Follow up
This report summarize all reinforcement types and specifies the members of a Reinforcement Group.
When printed from production, a set of data will be generated for each project. There is one document for each element type.
Report Setup
General report setup. All the fields have to be filled as it prints a sum row at the top of each page.

Figure 1: General report layout
Page max X and Page max Y define the maximum dimensions of the report page.
The X-axis corresponds to columns labeled A, B, C, etc., while the Y-axis represents rows numbered 1, 2, 3, etc.
Continuous Header Row specifies the starting row for both the header and footer. In this configuration, it begins at row 5.
Continuous Start Row, set to row 7, marks the beginning of the main content.
Continuous End Row, set to row 40, indicates where the main content concludes.
If the final field is completed, a summary will be generated at the top of each page.
Header setup:
Here is how the header is set up for this report.

Figure 2: Header and footer report setup
Assigning x and y values to each field facilitates the precise placement of designated information within the report.
As previously stated, the Continuous Header Row spans from row 0 to row 5 along the Y-axis.
The following fields are available for inclusion in the header and footer sections:
| Fields | Description |
| BUILDING | |
| DIVISION | |
| ELEMENT_TYPE | |
| FACTORY | |
| FLOOR | |
| PHASE | |
| PROJECT | |
| PROJECT_SUMMARY | |
| PROJECT_TRIMED | |
| REPORT_NAME | |
| REPORT_PAGE_NUMBER | |
| REPORT_PRINT_DATE | |
| REPORT_REVISION | |
| REPORT_REVISION_DATE | |
| REPORT_TITLE | |
| SELECTION_PRODUCT | |
| USER_DIVISION_CITY | |
| USER_DIVISION_COUNTRY | |
| USER_DIVISION_DESCRIPTION | |
| USER_DIVISION_FAX | |
| USER_DIVISION_NAME | |
| USER_DIVISION_PHONE | |
| USER_DIVISION_STREET | |
| USER_DIVISION_ZIPCODE | |
| USER_MOBILE | |
| USER_NAME | |
| USER_PHONE | |
| USER_SIGNATURE | |
| USER_TITLE |
Selection setup:
The standard setup for the selections.
Continuous setup:
All element-related configurations are managed within the Continuous setup section.
There is also a field for the Header Name, as the report is generated dynamically.

Figure 3: Continuous report setup
As previously demonstrated, a single row is defined within this section, serving as the foundation for the report and extending from row 7 to row 40.
The fields available for inclusion in this section are listed below.
| Fields | Description |
| ALL_MEASURE | One text for all the measures on bended reinforcement |
| CUTLENGTH | |
| CUTLENGTH_ROUNDED | |
| DIAMETER | |
| END_HOOK_1_DIRECTION | |
| END_HOOK_1_NAME | |
| END_HOOK_2_DIRECTION | |
| END_HOOK_2_NAME | |
| JIG_RADIUS | |
| MASS | |
| MASS_MESH_PER_M2 | |
| MEASURE_TABLE | |
| MESK_TYPE | |
| NO_IN_GROUP | |
| QUALITY | |
| RC_AREA | |
| RC_NAME | |
| RC_TYPE | |
| RC_WIDTH | |
| REMARK | |
| REVISION | |
| SHAPE_CODE | |
| SHAPE_PICTURE | |
| SUM | |
| X_ELEMENT_MARK_TABLE |
Print report
Information about where the report can be printed from.
From Report Tool
It is possible to select a standard set of content to be printed based on the information extracted from the report.
An option is also provided to save the selection.

Figure 4: Print report setup - Report tool
A dedicated selection section allows specification of the type of reinforcement to be included in the report.

Figure 5: Dedicated selection section
From Project Manager
The report is accessible for printing directly from the model viewer & from the element ids tab.

Figure 6: Print report setup - Project Manager - Model View

Figure 7: Print report setup - Project Manager - Element Ids
Selection of reinforcement types is required for inclusion in the report.

Figure 8: Selection of reinforcement types - Project Manager
From Resource Manager
The report is accessible for printing directly from the planning tab.

Figure 9: Print report setup - Resource Manager - Planning
Selection of reinforcement types is required for inclusion in the report.

Figure 10: Selection of reinforcement types - Resource Manager
Example
Printed page displayed below in Excel.

Figure 11: Excel report page