Introduction

This report lines up a summary of all the reinforcement for an element and shows it one element mark per page.  

The report is also called from production.

This is both a production and design report that can be printed from Report Tool, Resource Manager, Project Manager & Project Manager Cast Planning.

Report Setup

General report setup. All the fields have to be filled if you want a summary row at the end of each page.

Summary2.png

Page max X and Page max Y defined the maximum size of the report page.
The X-axis is the columns A, B, C etc. The Y-axis is the rows 1, 2, 3 etc.

Continuous Header Row defines in which row the header and footer start, and in this case, it starts from row 0.

Continuous Start Row (in this case from row 11) is where the main information starts and Continuous End Row (in this case until row 40) is where the main information ends.
 

Continuous Sum Row is a sum of listed values but is not relevant in this kind of report. 

Header setup: 
Here is how the header is set up for this report.

Header.png

As you can see we have different X and Y values for each field. This is done so the program knows where to put in the specific information into the report.

As mentioned above, the continuous header starts at row 0 to row 10 in the Y direction.

Here are the fields that can be added to the Header and Footer:

FieldsDescription
BUILDING 
DIVISION 
ELEMENTMARK 
FACTORY 
FLOOR 
PHASE 
PROJECT 
PROJECT_SUMMARY 
PROJECT_TRIMED 
REPORT_NAME 
REPORT_PAGE_NUMBER 
REPORT_PRINT_DATE 
REPORT_REVISION 
REPORT_REVISION_DATE 
REPORT_TITLE 
SELECTION_PRODUCT 
USER_DIVISION_CITY 
USER_DIVISION_COUNTRY 
USER_DIVISION_DESCRIPTION 
USER_DIVISION_FAX 
USER_DIVISION_NAME 
USER_DIVISION_PHONE 
USER_DIVISION_STREET 
USER_DIVISION_ZIPCODE 
USER_MOBILE 
USER_NAME 
USER_PHONE 
USER_SIGNATURE 
USER_TITLE 

Selection setup:
The standard setup for the selections.

Continuous setup:

The Continuous setup is where you set up all the information, in this case, about the reinforcement pr. element mark.

C_01.png

As you can see, here you define only one row because this row will be the bases for this report, from row 11 to 40 like shown further up. 

The fields you can add to this section are listed below.

FieldsDescription
RC_NAME 
RC_TYPE 
DIAMETER 
CUTLENGTH 
CUTLENGTH_ROUNDED 
AREA 
MASS 
MASS_MESH_PER_M2 
MESH_TYPE 
RC_WIDTH 
QUALITY 
JIG_RADIUS 
CONSTRUCTION_PART 
END_1 
END_DIRECTION_1 
END_2 
EMD_DIRECTION_2 
SHAPE_CODE 
REMARK 
REVISION 
SUM 

Print report

From Report Tool
It is possible to make the normal selection on what to print, based on the information you want to get out of the report.

You also have the option to save your selection.

PRINT.png

When clicking on "Print" you will be prompt with the option to create the path for the report. Select yes and the report will be created and stored under the project folder.

createdocpath.png

If you add elements or change anything in the project and print the report again, the report will make a new file and store the difference in the new file, so that you can see what has been changed in the project.

Example

REPORT_.png

Download