Elements Delivered and Erected on-site

Last modified by Thomas Gitsas on 2024/04/19 14:18

Set Elements to Erected in PM

After the elements are delivered, you can set them to "Erected" by selecting them on the model, then right-click and set to erect! This is relevant only if your company is also responsible for the erection.

1712910543949-951.png

The status will change to "Erected" and if you followed all the above steps, your model statuses should look (more or less) like this.

1712910617516-488.png

It is important to note that the status colour view is now really important, as anybody with a basic understanding of the system can look into the model to see exactly what the stage of the project is at any point in time.

Summary and Exercise

Important to remember is the summary and the follow-up tabs. Those will not be explained in this training, but if you want to find out more information on some of their functionality, feel free to look at the following video on YouTube.

IMPACT Tip of the Week #100 - Project follow-up - Precast concrete software - YouTube

To sum everything up, we have prepared an exercise that will help you glue all the training info together and start using the software as optimally as possible.

If you want to continue with the Final Summary Exercise press here.

You can move back to the start of the Rough Planning training by pressing here.

Otherwise, you can move back to the Table of Contents, by pressing here.